FAQCategory: ViewsWhen should I use Task Sheet?

When should I use Task Sheet?

1 Answers

Use the Task Sheet view to:

  1. View a list of tasks and task information quickly when you don’t need to see the information graphically over time.
  2. Review progress by comparing planned (baseline) dates and actual start and finish dates, and by checking the progress of each task.
  3. Establish sequential task dependencies by linking tasks. When you link tasks, you can see how a change in the duration of one task affects the start and finish dates of other tasks, as well as the project finish date.
  4. Assign personnel and other resources to tasks.