FAQCategory: TasksWhat is Start to Start dependency?

What is Start to Start dependency?

1 Answers

The Start to Start dependency forces a task to begin only at the same moment with its predecessor/successor or after its predecessor/successor started; the start of the predecessor/successor determines when the other starts. If a nonzero lag is present, it is added to the Start date.