FAQCategory: SchedulingDoes Project Plan 365 resolve the overallocation of a resource assigned 200% to a task?

Does Project Plan 365 resolve the overallocation of a resource assigned 200% to a task?

1 Answers

No. Project Plan 365 does not change neither the duration nor work of the tasks as part of the resource leveling method.