FAQCategory: ReportsCan the finish date be changed for the tasks with progress?

Can the finish date be changed for the tasks with progress?

1 Answers

Yes, the finish date for the tasks with progress can be changed and the % complete will change automatically:

  1. When editing the finish date of a task in the future when it has % complete, the % complete will decrease and the “Finish no earlier than” constraint will automatically apply to the task. 
  2. When editing the finish date of a task in the past when it has % complete, the % complete will increase and the “Finish no earlier than” constraint will automatically apply to the task.