FAQCategory: TasksAfter I applied time-off for a resource, the start and finish dates for tasks didn’t change.

After I applied time-off for a resource, the start and finish dates for tasks didn’t change.

1 Answers

In order to recalculate the changes made on the resource calendar, set the Task Type to Fixed Units.