FAQCategory: SchedulingCan I have a resource assigned to the task and the resource availability would drive the calculation of the finish date?

Can I have a resource assigned to the task and the resource availability would drive the calculation of the finish date?

1 Answers

You need to make the changes on the resource calendar. Then, you need to set the task type to Fixed Units or Fixed Work depending on your needs. The app will automatically calculate the duration of your task based on the resource calendar.