FAQCategory: SchedulingCan I reschedule uncompleted work to start after a different date than the current or Status Date?

Can I reschedule uncompleted work to start after a different date than the current or Status Date?

1 Answers

If you don’t specify a date, Project Plan 365 uses the current or status date. The unfinished work can be rescheduled to start after a different date by going to menu Project – Update Project and from the “Reschedule uncompleted work to start after:” section select a different date from the date picker. Set the desired options and click OK.