FAQCategory: SchedulingCan I set the Maximum Cost for the entire project?

Can I set the Maximum Cost for the entire project?

1 Answers

To set the Maximum Cost for the entire project, first make sure you have the “Deadline and MaxCost” method set in the menu File – Options – Schedule Tab. Then go to menu Project – Project Information and in the Maximum Cost field type in the desired maximum cost for the entire project. Click OK to save the changes.