Do you have a work availability field?
1 Answers
To see the Work column, go to Format – Insert Column – In the Field Name box select column Work and click OK. The work availability column will appear in the grid. If you want to see the working hours per day, please look at the Resource Calendar. To do this, go to menu Project – Change Working Time and select the desired calendar.