FAQCategory: SchedulingDoes the question mark in the Duration box have any meaning?

Does the question mark in the Duration box have any meaning?

1 Answers

The default duration for new tasks has a question mark (1d?). The question mark indicates that the duration is an estimate. Add a question mark to any duration estimate. Remove the question mark to indicate a committed duration.