Does the Subproject’s Wbs reflect the WBS numbering flow in the master or does the Subproject retain its Wbs numbering?
1 Answers
The subproject will retain the WBS numbering. Only the Summary Subproject Task will have a calculated WBS based on his position in Master Project.