FAQCategory: SchedulingDoes the Subproject’s Wbs reflect the WBS numbering flow in the master or does the Subproject retain its Wbs numbering?

Does the Subproject’s Wbs reflect the WBS numbering flow in the master or does the Subproject retain its Wbs numbering?

1 Answers

The subproject will retain the WBS numbering. Only the Summary Subproject Task will have a calculated WBS based on his position in Master Project.