How a Finish date for a task is calculated?

1 Answers

Finish date can be calculated or entered. If you do not type a finish date, application calculates it based on such things as relationships, calendars, and the scheduling method.

If resources are assigned, Project Plan 365 also considers the resource calendar and assignment units. If you type a finish date, will be set automatically a Finish No Earlier Than constraint and uses the date you type as the constraint date.

Example: You need to filter for all finish dates scheduled after March. You filter on the Finish field to see only those tasks scheduled with a finish date beyond March 31.