How can I add a base calendar to a resource?

1 Answers

After creating a base calendar for a specialized schedule (other than the Standard project calendar) you can base a resource’s working times on this calendar. In the View menu click Resource Sheet. In the Resource Name select the desired resource. In the Base calendar column select the calendar you want to be assigned for the specific resource.