How can I add Start and Finish dates to appear next to the bars in Gantt Chart?
1 Answers
If you want the Start and Finish dates to appear in the Gantt Chart, please go to the Format menu-Bar Styles option, select the Text Tab. Then, from Left – select the column Start and from Right – select the column Finish. Press OK and your Start and Finish dates will be displayed in the Gantt Chart.