How can I change the start and finish dates for a task?
1 Answers
There are two ways to change the start and finish dates for a task:
1. Select the desired task, go to the Task menu and select Task Information option. Change the start and finish dates and click on “OK” button for the changes to take effect.
2. Click on the placeholder inside the Start/Finish cells to open the dropdown and select a new start/finish date.