FAQCategory: TeamHow can I edit a task using the Team Member Planner dialog?

How can I edit a task using the Team Member Planner dialog?

1 Answers

To edit a task using the Team Member Planner dialog go to menu “Team” – “Team Member Planner”. Select the desired team member from the drop-down list. In the Timeline panel, select the desired task only from the current project and change its start date / finish date and duration and then click “Ok”.
Note: Complete tasks that have %Complete – 100% are not displayed in the Team Member Planner dialog.