FAQCategory: SchedulingHow can I reschedule uncompleted work in a project?

How can I reschedule uncompleted work in a project?

1 Answers

To reschedule uncompleted work in your project, go to menu Project – Update Project, check “Reschedule uncompleted work to start after” option, select a date from the date picker then click OK. All tasks will be updated and uncompleted / unstated work will be rescheduled.
Note: If you don’t specify a date, Project Plan 365 uses the current or status date.