How can I see the Early Start for tasks?
1 Answers
To see the Early Start for tasks, select the Gantt View – in the Project menu – click Table – Schedule – Insert the Early Start column by going to the Format menu – Insert Column.
How can I see the Early Start for tasks?
To see the Early Start for tasks, select the Gantt View – in the Project menu – click Table – Schedule – Insert the Early Start column by going to the Format menu – Insert Column.