FAQCategory: SchedulingHow can I see the Late Finish date for tasks?

How can I see the Late Finish date for tasks?

1 Answers

To see the Late Finish for tasks, select the Gantt View – in the Project menu – click Table – Schedule – Insert the Late Finish column if it is not appearing in the grid by going to the Format menu – Insert Column.