How can I set an interim plan for selected tasks?
To set an interim plan for selected tasks, in the desired project, select the desired tasks (using the Shift or Ctrl keys), then go to menu Project – Set Baseline. Check the Set interim plan option – select the desired field from the Copy drop down menu – select the desired field from the Into drop down menu – select the Selected Tasks option then click OK. The fields selected from the Into dropdown will contain the values from the Copy dropdown.
Note: If the selected fields are StartX/FinishX, then only the Start/Finish values will be copied. If the fields are Baseline, then all the values for the baseline fields will be copied.