FAQCategory: FormatHow can I show the Resource Initials next to the bars?

How can I show the Resource Initials next to the bars?

1 Answers

In order to add the Resource initials in the Gantt Chart, go to the Format menu – Bar styles, select the Text tab, chose in which side of the Gantt Chart you want to display the Resource name initials and select the “Resource Initials” field. Press “OK” and the Resource Initials will be displayed in the Gantt Chart.