FAQCategory: SchedulingHow can I update multiple tasks using the Update Tasks functionality?

How can I update multiple tasks using the Update Tasks functionality?

1 Answers

To update multiple tasks using the Update Tasks functionality, first select the desired tasks, then go to menu Tasks – Mark on Track – Update Tasks. Set the desired values for %CompleteActual and Remaining Duration or Actual Start and Finish Dates then click OK for the changes to be applied.