FAQCategory: SchedulingHow can I update the entire project with 0% or 100% complete only?

How can I update the entire project with 0% or 100% complete only?

1 Answers

To update your project with 0% or 100% complete only, go to menu Project – Update Project, make sure the “Set 0% or 100% complete only” option is checked under the “Update work as complete through:” section, select a date from the date picker and click OK.
Note: If you don’t specify a date, Project Plan 365 uses the current or status date.