FAQCategory: SchedulingHow can I update the Remaining Duration of a task using the Update Tasks functionality?

How can I update the Remaining Duration of a task using the Update Tasks functionality?

1 Answers

To update the Actual Duration of a task, go to menu Tasks – Mark on Track – Update Tasks. In the Update Tasks dialog set the desired value in the Remaining dur: field then click OK for the changes to be applied.
Note: When you adjust the remaining duration for a task, Project calculates the duration and percent work complete according to the formulas Duration = Remaining Duration + Actual Duration and Percent Complete = Actual Duration / Duration