To add progress to a task in your project directly from the Gantt Chart, follow the steps below:
- Locate in the right side chart of a Gantt view its corresponding taskbar.
- Place the mouse to the start portion of the taskbar, when you will notice that the mouse indicator changes to a specific icon.
- To indicate progress for a task, hold down the mouse and drag to the right the gray displayed bar inside the task bar to increase the value for the % complete field.
- Release the mouse when you are satisfied with the entered progress.
- The % complete corresponding to the task is represented by a darker and thinner bar inside the bar of the task.