FAQCategory: CalendarHow do I change the working time for a resource?

How do I change the working time for a resource?

1 Answers

To change the working time of a resource, you need to look in the resource calendar. To do this, go to the Project menu, click the Change Working Time  button and then select from For calendar list any individual resource. Or you could open Resource Information for the resource and click Change Working Time button. For the desired resource, change the working time from Work Weeks tab – Details.