FAQCategory: SchedulingHow do I clear the baseline?

How do I clear the baseline?

1 Answers

To clear the baseline for the entire project, go to the menu Project – Set Baseline – Clear Baseline. In the Clear Baseline dialog select the “Clear baseline plan” field option and from the drop-down menu select the desired Baseline – select the “Entire project” option and click the “OK” button.