How do I copy multiple tasks?
1 Answers
If you want to copy multiple tasks or resources at a time, first you have to select the desired rows using SHIFT (for contiguous selection of rows) or CTRL (for noncontiguous selection of rows) keys, select the destination row and then use the Paste command to copy the selected rows. The copied tasks or resources will be inserted above the selected destination row and the IDs of the remaining tasks or resources will be automatically renumbered.