FAQCategory: FormatHow do I format the nonworking time from the Gantt Chart?

How do I format the nonworking time from the Gantt Chart?

1 Answers

To format the nonworking time from the Gantt Chart, go into the Gantt Chart View – on the Format Menu – click Timescale – select the Non-working time tab – make the desired settings and click OK.