FAQCategory: TasksHow do I leave the task without start and finish dates?

How do I leave the task without start and finish dates?

1 Answers

If you want the tasks in your project to appear with the Start, Finish and Duration fields blank, please set the schedule mode of your tasks to Manually Scheduled. In order to do that, go to the File menu – Options, select “Schedule” tab. From “New Tasks Created” field select “Manually Scheduled” and click on “OK”.