How do I roll up to a total project % complete?
1 Answers
To change the %complete for the entire project, please insert the Summary Project in your plan by going to menu File-Options-Advanced tab and check Show Project Summary Task. Then, in the Gantt Chart view, change the percent complete for the project summary task.