How do I set multiple baselines for selected tasks?
1 Answers
To set multiple baselines for selected tasks, in the desired project, select the desired tasks (using the Shift or Ctrl keys), then go to menu Project – Set Baseline – from the Set baseline field, select a different Baseline option, select the Selected Tasks option then click OK.