FAQCategory: TasksHow manual tasks interact with scheduling fields?

How manual tasks interact with scheduling fields?

1 Answers

Manual tasks and interaction with other scheduling fields:

Duration, Start and Finish date can be text, number or dates -this values not used in scheduling process.

Constraints – can be used but this value will be ignored.

Resources – can be assigned to tasks, these values are not used in the scheduling process.

Dependencies -can be used but this value will be ignored.

Project and resource calendars – will be ignored.