How manual tasks interact with scheduling fields?
1 Answers
Manual tasks and interaction with other scheduling fields:
Duration, Start and Finish date can be text, number or dates -this values not used in scheduling process.
Constraints – can be used but this value will be ignored.
Resources – can be assigned to tasks, these values are not used in the scheduling process.
Dependencies -can be used but this value will be ignored.
Project and resource calendars – will be ignored.