How Peak Units field (resource-timephased field) is calculated?
1 Answers
The value in the Peak Units field is the maximum effort a resource is working on all assigned tasks, as shown over a period of time.
How Peak Units field (resource-timephased field) is calculated?
The value in the Peak Units field is the maximum effort a resource is working on all assigned tasks, as shown over a period of time.