How Set Baseline works in a MPP file?
1 Answers
To set a Baseline for the entire project click Project – Set Baseline. In the Set Baseline dialog select “Entire project” and click the “OK” button. This way the Baseline for the Entire Project will be set. The Baseline will be set when you Save your project.