FAQCategory: SchedulingHow the Actual Cost of an Assignment is calculated?

How the Actual Cost of an Assignment is calculated?

1 Answers

The Actual Cost of an Assignment is calculated using a formula similar to the cost formula. The main difference is that instead of the assignment Work field, the Actual Work field value is used. Project Plan 365 calculates this value when you adjust a task’s percentage complete field. Actual Work is calculated using the formula:
Assignment Actual Work = Work * Assignment’s Task Percent Complete

Contact
Chat