FAQCategory: SchedulingHow the Remaining cost for a resource assignment is calculated?

How the Remaining cost for a resource assignment is calculated?

1 Answers

The remaining cost is calculated by Project Plan 365 for an Assignment, a Resource or a Task by simply subtracting Actual Cost from Cost: RemainingCost = Cost – ActualCost
 