FAQCategory: TasksHow to make the next task start at end of the previous task?

How to make the next task start at end of the previous task?

1 Answers

To make a task start when another task is finished, you need to establish a Finish to Start dependency in Predecessors column or in Task Information dialog under the Predecessors tab.