How to see the percentage of work for each month? |
1 Answers
In order to see the %Work Complete for a specific month, first go to Format menu – Insert, select the %Work Complete column an click OK. Then go to Project menu – Autofilter. Click on the autofilter arrow next to the column heading of the Start column and check only the month you want. The autofilter arrow and the column name will turn in blue.