FAQCategory: TasksI am not able to change the constraint type of a manual task.

I am not able to change the constraint type of a manual task.

1 Answers

The Constraints Type and the Constraint Date boxes are grayed out for Manual Tasks. Manual Tasks have the main purpose to not have its Start, Finish dates and Duration modified by the Planner. For this reason, manual tasks should not have any kind of constraints. 