Is Project Plan 365 going to alert me when setting an incorrect task dependency?
1 Answers
Project Plan 365 will alert you when you set the following incorrect task dependencies cases:
- Circular dependency – when tasks are already liked together;
- Task chain dependency – when tasks are already linked through another task chain;
- Dependency to the task itself – when making a task a predecessor of itself;
- Dependency between a summary task and a subtask – when linking a summary task to one of its subtasks;
- Linking predecessor task twice to the same successor;
- Adding invalid predecessor value;
- SF and FF dependency for a summary task;
- Linking non-existent tasks;
- Adding invalid lead/lag time value.