FAQCategory: TasksIs Project Plan 365 going to alert me when setting an incorrect task dependency?

Is Project Plan 365 going to alert me when setting an incorrect task dependency?

1 Answers

Project Plan 365 will alert you when you set the following incorrect task dependencies cases:

  • Circular dependency – when tasks are already liked together;
  • Task chain dependency – when tasks are already linked through another task chain;
  • Dependency to the task itself – when making a task a predecessor of itself;
  • Dependency between a summary task and a subtask – when linking a summary task to one of its subtasks;
  • Linking predecessor task twice to the same successor;
  • Adding invalid predecessor value;
  • SF and FF dependency for a summary task;
  • Linking non-existent tasks;
  • Adding invalid lead/lag time value.