What does the “Completed Tasks” report?
1 Answers
The “Completed Tasks” report displays a list with task information for tasks that are 100% complete (have both actual start and finish dates saved).
What does the “Completed Tasks” report?
The “Completed Tasks” report displays a list with task information for tasks that are 100% complete (have both actual start and finish dates saved).