What impact has not adding resource assignments to the schedule?
1 Answers
If you don’t assign resources to tasks in your project, application calculates the schedule using durations, task dependencies, constraints, and project and task calendar information. If you do assign resources, the tasks are also scheduled according to resource calendars and assignment units, providing for more accurate scheduling.