FAQCategory: ViewsWhat information can I update in Task Information dialog inside the All Tasks Phone View?

What information can I update in Task Information dialog inside the All Tasks Phone View?

1 Answers

In the All Tasks Phone View, using the Task Information dialog,  the application allows you to edit the Name, Percent Complete, Schedule Mode, Duration, Start Date, Finish Date, Priority, Hide task bar option, Roll up Gantt Bar to Summary option, Predecessors, Resources, Deadline, Constraint type,  Constraint date, Task type, Calendar, WBS Code, Mark task as milestone option, and to add Notes. 