FAQCategory: Project TrackingWhat is Baseline0-10 Cumulative Work field field?

What is Baseline0-10 Cumulative Work field field?

1 Answers

The Baseline0 through Baseline10 Cumulative Work fields contain the amount of time scheduled for all resources assigned to tasks, accumulated over time, when the baseline was set.