FAQCategory: Project TrackingWhat is BCWS (Planned Value or PV) field?

What is BCWS (Planned Value or PV) field?

1 Answers

The BCWS (budgeted cost of work scheduled) field contains the cumulative timephased baseline costs up to the status date or today’s date.

Contact
Chat