FAQCategory: SchedulingWhat is the Actual Cost of a task?

What is the Actual Cost of a task?

1 Answers

The actual cost of a task is the added actual costs of all assigned resources (or the added costs of all child tasks, in the case of a summary task), plus any fixed costs set for the task, weighted by the task percent complete value.