FAQCategory: SchedulingWhat is the Critical Path Method?

What is the Critical Path Method?

1 Answers

The Critical Path methodology identifies the paths of tasks most likely to impact the project completion date. This technique is used to help project managers to determine the shortest possible project duration and the level of flexibility that exists in the project. The critical path method calculates the early dates (Early Start and Early Finish), late dates (Late Start and Late Finish) and total slack.

Contact
Chat