1 Answers

Add the Peak Units field to the timephased portion of the Task Usage or Resource Usage view when you want to display the maximum effort for which the resource is designated to work on an assignment, as distributed over time. This is particularly useful when you have applied a work contour other than the default flat work contour. The Peak Units field shows the points in time in which more effort is being applied to the assignment.