FAQCategory: SchedulingWhen I should use Peak Units field (resource-timephased field)?

When I should use Peak Units field (resource-timephased field)?

1 Answers

Add the Peak Units field to the timephased portion of the Resource Usage view when you want to display the maximum effort for which the resource is designated to work on all assigned tasks over the selected time period.

Contact
Chat